Anwyl homes ( Prestatyn)

Added: Monday 23rd September 2013

This contract consisted of the following

Excavate area and remove spoil

Install log edgings 

Install pcc edging kerbs for pathways

Import and lay MOT type 1 stone

Lay geo- textile membrane 

Import and lay 90 cubic meters play spec bark chippings 

Install 150 meters of play spec bow top fencing

Install 3 x pro safe self closing gates

Installation of the following play equipment

1 x basket swing 

1 x  two seat cradle swing

1 x spinning dish 

1 x double elephant spring rocker

2 x climbing poles 

1 x adventure trial

1 x picnic table 

1 x bench

This contract was carried out for Anwyl homes and took approximately 5 weeks to complete.